Arian Zanjan combined cycle
Arian combined cycle power plant (Zanjan 2) includes two gas units with a capacity of 183 MW each and a steam unit with a capacity of 180 MW, with a total capacity of 546 MW. The technical specifications of this project include its MAP2B turbine and three-pressure boiler.
The first unit of this power plant was synchronized with the national power grid on the 9th day and the second unit on the 17th day of June 1401.
The employer of this project, which started in the beginning of 1998, is North and South Energy Development Company and its consultant is Quds Niro Engineering Company. This power plant is located 82 km from Zanjan-Tabriz highway, Sarchem intersection.
It is worth mentioning that Ariyan Combined Cycle Power Plant (Zanjan 2) is the 176th unit of the Power Plant Construction and Development Company that was successfully synchronized.